Plant Room Strip Out Hull

Plant room strip out in Hull and across the East Riding

In Hull the calls come from food and seafood factories, hospital and university buildings, offices and commercial schemes in the centre, and the units on the estates around the city. We take the redundant mechanical and electrical plant out, get it off site and set the replacement down on its bases, all to the M&E contractor’s programme.

We cover Hull, Hessle, Cottingham, Anlaby, Willerby and Hedon, and further out to Beverley, Brough, Goole and Grimsby. Photographs of the room and the route out are enough for a desktop survey, with a quote usually the same day. We work at night or through a shutdown wherever the building must keep going.

What a strip out covers

Our crew takes redundant plant apart until each piece fits the way out, then rigs it clear and off site. Boilers and chillers, air handling units, pumps and tanks, generators and switchgear, and the dead pipework and steel all come under it. Then the replacement plant is brought in and landed level on its bases, ready for the M&E contractor to connect.

What comes out of a Hull plant room

Plant Where it sits How it comes out
Boilers and calorifiers Ground floor boiler houses and low plant rooms Casing stripped, parted into cast sections and walked out on skates
Chillers and condensers Flat roofs and fenced compounds beside the building Lifted off whole from the street, or cut to modules on the roof
Air handling units Rooftop frames and ceiling-height plant decks Fan and coil sections unbolted and lowered one at a time
Pumps, pressurisation sets and tanks Boiler houses and tank rooms Unbolted, slung from a gantry and trolleyed along the corridor
Generators, transformers and switchgear Switchrooms and standby rooms in an energy centre Hauled on machine skates behind a winch, then craned onto the trailer
Redundant pipework and support steel Wall runs, risers and overhead racks Cold cut into manageable lengths, cleared as each area empties

A light unit wedged behind a column can dictate more of the method than the biggest boiler in the room, because the plan follows the hardest journey to the door. Our plant room strip out service page walks through each stage.

Contact us

Get In Touch

Please leave a few details and a member of our plant room strip out team will be in touch to discuss your requirements in more detail.

    Where we work in and around Hull

    Five kinds of Hull building send us this work.

    Food and seafood factories

    Freezer packs, refrigeration plant and boilers leave the city’s food plants inside short stops, timed around cleaning. See our food and beverages page.

    University, college and school buildings

    Heating and ventilation plant in teaching buildings is changed in the vacations, with the start of term as the fixed end. See our education page.

    The Old Town and city-centre offices

    Roof chillers and basement boilers on commercial buildings in the centre come out with tenants still working below. See our HVAC page.

    Sutton Fields and the estates

    Rooftop units, compressor rooms and boiler houses on engineering and component factories are cleared in a planned stop. See our industrial page.

    Wards, clinics and health centres

    Chillers and air handling units in the city’s healthcare buildings are swapped only after the new plant is running, on hours the estates team sets. See our healthcare and pharma page.

    Access and planning for a Hull plant room strip out

    Settled at survey, before a Hull job takes a date:

    • The biggest piece after splitting. Section, panel and flange joints give the split points, and whatever the biggest piece then weighs tells us if a crane has to come.
    • What the floors and yard will carry. A jacked load presses hard on one spot of slab, and much of Hull stands on reclaimed land, so we check the route inside and the crane’s standing outside.
    • Keeping the building open. Access hours, noise, lift bookings and boarded routes are agreed with the building manager.
    • Road space and lay-down. Lifting over a building closes some of a road or car park and needs a spot to land the old unit. We apply for the traffic management and road closure with Hull City Council, or East Riding of Yorkshire Council beyond the city boundary.
    • A crane from outside, or a route inside. A crane lift is quicker and costs the hire and the closure. An internal route costs labour, protection and hours. Near the estuary the crane day also carries a wind check and an agreed fallback date.

    Before anything is lifted

    Nothing is cut until other trades have finished their part. The M&E contractor isolates, drains and locks off each system and puts that in writing. An F-gas certified engineer recovers the refrigerant from chillers and freezer plant. If asbestos turns up in the refurbishment and demolition survey, a licensed contractor removes it first.

    We set our dates behind all three at quoting stage. Where old and new plant have to share the room for a while, that overlap goes into the same programme.

    Postcodes and areas we cover

    We cover every HU postcode and the districts around the city:

    • Hull: city centre, the Old Town, Sutton, Bransholme, Anlaby, Willerby and Sutton Fields
    • East: Hedon, Preston, Withernsea and Hornsea
    • West and north: Hessle, Cottingham, Beverley, Brough and Driffield
    • Wider area: Goole, Scunthorpe, Grimsby, Immingham, Selby and York

    We strip out plant rooms right across the UK.

    Why Hull firms choose Synergy Lifting for plant room strip out

    • Hygiene rules and clinical hours are part of the method. Food plants and healthcare buildings across Hull set their own routes and times, written into the plan with the site team at survey.
    • A single order from street to plinth. The crane outside, the riggers in the plant room, the wagon taking the old plant away and the new unit landed on its base all come from us.
    • Old and new handled in one visit. Where the replacement arrives as the redundant unit leaves, one mobilisation and one road closure cover both.
    • Qualified and accredited. CPCS and NPORS operators, lifts planned to BS 7121, equipment inspected under LOLER and PUWER, SSIP approved, Constructionline Gold Member, certified to ISO 9001 and ISO 14001, and members of the Construction Plant-hire Association.

    How a plant room strip out works

    1. Tell us what is in the plant room, where it sits in the building, and send photographs following the route out.
    2. Our survey settles that route and where each unit will be split.
    3. Next come the method statement, risk assessment and lift plan, and our dates go in once the isolations are fixed.
    4. Our crew dismantles the plant, moves it out along boarded floors and loads our wagons.
    5. New plant goes down level on its bases and the M&E contractor takes over.

    Common questions

    Does the weather on the Humber put a roof lift at risk?

    It can move the crane day, so a fallback date is agreed at planning. Work inside the plant room carries on, so a windy morning costs the lift and leaves the rest of the programme where it was.

    Our plant room is in the Old Town, on a narrow street. Can the old plant still come out?

    Yes. Where a nearby street or car park is wide enough, Hull City Council closes it for the day and a crane lifts from there. Where no position reaches the plant, it is split and brought down through the building to a loading point.

    Can the building stay open while the plant comes out?

    Usually, yes. Most of this work happens in buildings that keep running, so the route is protected, the hours are agreed with the building manager, and the heavy moves go at night or over a weekend where that suits everyone. On a heating or cooling system the building cannot lose, the new plant goes in and is proven before the old plant comes out.

    Who isolates and drains the plant before you start?

    Your M&E contractor, with the isolation, drain down and lock-off signed off in writing before we cut anything. Refrigerant recovery belongs to an F-gas certified engineer and asbestos to a licensed contractor, so we plan our dates around both. We agree at quoting stage who is covering what.

    Get a quote for a plant room strip out in Hull

    Send us what the plant is, where in the building it sits and whether new plant is going in, with photographs of the plant room and the route out.

    We also provide plant room strip out in Grimsby, York, Doncaster and Lincoln. See all the plant room strip out locations.