Plant room strip out in Doncaster and across South Yorkshire
We strip out plant rooms in Doncaster for the distribution sheds, the works in the lower Don Valley, utility and waste sites, town centre landlords, and the school, college and hospital estates. What leaves is the redundant mechanical and electrical plant: switchgear and transformers, standby generators, chillers, condensers, air handling units, pumps, tanks, calorifiers and boilers. We work to the M&E contractor’s programme.
We cover Balby, Bentley, Armthorpe, Thorne and Mexborough, out to Rotherham, Barnsley and Goole. Photographs from the plant room to the loading door bring a desktop survey and price the same working day, and most of the heavy work lands in shutdowns and at weekends.
What a strip out covers
Plant is reduced to pieces the route will take, rigged out and cleared from site, and new plant comes back the same way to be set level on its bases. Pipework, electrical work and commissioning stay with your M&E contractor.
What comes out of a Doncaster plant room
| Plant | Where it sits | How it comes out |
|---|---|---|
| Boilers and calorifiers | Ground floor boiler houses and basements | Burner and insulation off, shell parted to the doorway |
| Chillers and condensers | Shed roofs, yard plinths and compounds | Slung off in one from the yard, or reduced on the roof deck |
| Air handling units | Roof decks and internal plant rooms | Casing panels off first, then the coils and the fan deck |
| Pumps, pressurisation sets and tanks | Tank rooms, basements and riser cupboards | Toe jacked off the plinth, rolled out on skates |
| Generators, transformers and switchgear | Energy centres, switchrooms and comms rooms | Gantried off the base and skated out |
| Dead pipework and support steel | Risers, ceiling voids and the room itself | Cold cut where it is bracketed, bundled and carried out |
Plan around the heaviest item and the small one in a tight corner will stop the job, so the worst route out sets the method. The plant room strip out service page walks through each stage.
Contact us
Get In Touch
Please leave a few details and a member of our plant room strip out team will be in touch to discuss your requirements in more detail.
Where we work in and around Doncaster
Most of our Doncaster plant room work starts in the sheds by the motorway junctions.
Distribution sheds and logistics parks
Boiler plant, pump sets and rooftop cooling come out of the units at iPort and Balby Carr while trailers keep arriving. See our industrial sector page.
Steel and process works in the lower Don Valley
Boiler houses and compressor rooms behind the works from Mexborough through Swinton take the line down with them when they stop, so the job waits for a booked shutdown. See our plastics and metals page.
Substations, utilities and waste sites
Transformers, switchgear and standby sets are changed inside a booked outage, and plant in the recycling and transfer buildings comes out in planned downtime. Both are covered on our power and renewables and waste and recycling pages.
Town centre offices and retail blocks
A landlord changing basement boilers or roof chillers keeps the tenants in, so the sequence is built around one goods lift and the hours they will wear. See our HVAC page.
Schools and colleges
Old boilers and air handling units come out over the holidays, and the caretaker gets the keys back on the day agreed. See our education page.
Hospital estates and clinics
Old heating and cooling plant leaves a building treating people only after the new set has been proven on load. See our healthcare and pharma page.
Access and planning for a Doncaster plant room strip out
Five things get settled with the site before a Doncaster strip out takes a date:
- Where the crane stands, and where plant is laid down. A crane lifting over the building needs part of a road, plus a lay-down beside it. The traffic management and road closure goes through City of Doncaster Council, and through Rotherham council where the building stands at Swinton.
- Where each unit comes apart. The flange and panel joints decide the split, and the split decides the weight of the biggest piece.
- The building keeps working around us. The hours we work, the protection on the route and the lift we are given, settled with the building manager before a date.
- Craned off the roof, or taken out at ground level. Crane, labour and hours come out very differently for each, and where both are possible the survey prices both.
- What the route will carry underfoot. A jacking point puts far more through a square inch than the floor was built for, and older buildings along the lower valley stand on made ground.
Before anything is lifted
Our crew books in only after three sign-offs from other trades. Isolation, drain down and lock-off are done by your M&E contractor and confirmed in writing before we cut anything. Refrigerant recovery goes to an F-gas certified engineer, and we follow the certificate. Anything a refurbishment and demolition survey picks up goes to a licensed contractor for clearance and certification.
At quoting stage all three sit in the programme beside the new plant’s delivery date. Our crew starts once the last of them lands.
Postcodes and areas we cover
Work comes in from across the DN postcodes:
- Doncaster: town centre, Hexthorpe, Balby, Wheatley, Bessacarr and Bentley
- North and east: Armthorpe, Adwick, Askern, Dunscroft, Hatfield and Thorne
- South and west: Rossington, Bawtry, Tickhill, Conisbrough, Denaby and Mexborough
- Wider area: Rotherham, Swinton, Barnsley, Worksop, Goole and Scunthorpe
We strip out plant rooms right across the UK.
Why Doncaster firms choose Synergy Lifting for plant room strip out
- Live sites are normal ground. Trailer movements, shift changes and permit systems go into the plan before we arrive instead of being met on the day.
- Nothing is left in the plant room. The old units, redundant steel and cut pipework leave on our wagons, and the floor is swept before the room is handed back.
- Everything on one contract. The machine outside, the crew rigging in the plant room, the haulage and the new unit on its bases all sit with us.
- Qualified and accredited. CPCS and NPORS operators, lifts planned to BS 7121, equipment inspected under LOLER and PUWER, SSIP approved, Constructionline Gold Member, certified to ISO 9001 and ISO 14001, and members of the Construction Plant-hire Association.
More than plant room strip out
Other work a Doncaster strip out pulls in:
How a plant room strip out works
- Send the plant schedule, the replacement if there is one, and photographs of the way out to the yard.
- A survey then fixes the way out and the split points for each unit.
- We draw up the method statement, risk assessment and lift plan, and hang our dates off the isolations.
- Breaking down, moving and loading out all happen inside the hours the site has agreed.
- The replacement lands on its bases, levelled and ready to connect.
Common questions
Our chiller sits on a shed roof at iPort. Can the lift go in while trailers are moving?
Yes, from a fenced section of yard agreed with your site team, with the exclusion zone marked before the crane arrives and the lift timed to a gap between arrivals.
A railway runs along the back of our Mexborough works. Does that change the job?
Where the load-out comes within reach of the line, yes. The rail operator sets the clearances and decides whether a possession is needed, so tell us at enquiry how close the line runs.
Can the building stay open while the plant comes out?
Usually, yes. Most of this work happens in buildings that keep running, so the route is protected, the hours are agreed with the building manager, and the heavy moves go at night or over a weekend where that suits everyone. On a heating or cooling system the building cannot lose, the new plant goes in and is proven before the old plant comes out.
Who isolates and drains the plant before you start?
Your M&E contractor, with the isolation, drain down and lock-off signed off in writing before we cut anything. Refrigerant recovery belongs to an F-gas certified engineer and asbestos to a licensed contractor, so we plan our dates around both. We agree at quoting stage who is covering what.
Get a quote for a plant room strip out in Doncaster
- Phone: 01302 238 334
- Email: doncaster@synergy-lifting.co.uk
Send what the plant is, which floor it is on and whether new plant is going in, with photographs of the room and the route out to the yard.
We also provide plant room strip out in Sheffield, Chesterfield, Leeds and York. See all the plant room strip out locations.