Plant room strip out in Ipswich and across Suffolk
In Ipswich we get called by health estates, schools and colleges, offices round the wet dock and in town, and food plants and A14 sheds with their own plant rooms. We take the old M&E plant apart, carry it off site and set the new units on their bases. The M&E contractor runs the programme and we work to it.
We cover Ipswich, Kesgrave, Martlesham, Woodbridge and Felixstowe, out to Stowmarket, Bury St Edmunds, Sudbury and Colchester. Photographs of the plant and the way out bring a same-day quote in most cases. Evening, weekend and shutdown working suits buildings that cannot close.
What a strip out covers
It covers anything in the room that is finished with: boilers and calorifiers, chillers, AHUs, pumps and pressurisation sets, tanks, transformers, generators and switchgear, and the old pipework and steel between them. We break each item down until it fits the route and take it away. New plant comes in the same way and goes down level on its bases, ready for connection.
What comes out of an Ipswich plant room
| Plant | Where it sits | How it comes out |
|---|---|---|
| Switchgear, transformers and standby generators | Low-ceilinged switchrooms | Jacked at the frame corners, then skated to the waiting wagon |
| Boilers and calorifiers | Below ground, or behind one street-level door | Flue and casing off, sections parted and skated to the hatch |
| Chillers and condensers | Roofs, or a caged compound by the service yard | One crane pick where one reaches, or split into modules and lowered inside |
| Air handling units | Roof plant decks and mid-floor plant rooms | Panels and fan sections separated at bolted joints |
| Pumps, tanks and pressurisation units | Tank rooms and risers | Raised off the plinth by gantry, skated to the door |
| Redundant pipework and steel | Overhead racks, wall brackets and floor stands | Cut cold into lengths that clear corridor corners |
We plan around the item with the most awkward way out, which can be a small unit behind a tight door. Our plant room strip out service page sets out each stage.
Contact us
Get In Touch
Please leave a few details and a member of our plant room strip out team will be in touch to discuss your requirements in more detail.
Where we work in and around Ipswich
Ipswich work runs from the A14 to the waterfront.
Warehouses feeding the container traffic
Heating plant, standby generators and switchgear come out of warehouses along the A14 while forklifts carry on across the floor. See our industrial sector page.
Food plants and their energy centres
Boiler houses and refrigeration plant behind processing, milling and packing sites come out in shutdowns already in the calendar. See our food and beverages page.
Technology and trade units on the edge of town
Rooftop units and small boiler rooms on engineering and technology units at Ransomes, Whitehouse and Martlesham are changed with the workshop below kept running.
Offices by the wet dock
Chillers off the roof and boilers from the basement leave offices squeezed between the water and narrow streets, with tenants working above. See our HVAC page.
Hospital and health estates
Cooling and ventilation plant on health sites is replaced one system at a time, so wards keep their heating, and the estates team sets when our crews use the corridors. See our healthcare and pharma page.
Schools and colleges across Suffolk
Boilers and air handling plant leave teaching buildings during the summer break, when the corridors and lifts are free for us to use. See our education page.
Access and planning for an Ipswich plant room strip out
An Ipswich survey settles these five points.
- Over the top or through the middle. A roof lift costs a crane day and a closure. The internal route costs crew hours, floor protection and lift bookings. When wind shuts the Orwell Bridge, A14 traffic diverts through the town, so a roof lift gets a spare date.
- Where each unit splits. Panel joints and flanges give the break points, and whether we crane on the waterfront rests on the heaviest piece left.
- A place to stand and to land. Craning over a building takes a lane or part of a car park, plus space to land the old unit. Suffolk County Council handles the closure and traffic management, and we make the application.
- Occupants carrying on. The building manager tells us when we can work, how loud, and when the goods lift is ours. Corridors on the route get protected.
- Slabs, voids and made ground. A unit on skates sits on a few small points, and a suspended floor has to carry them. By the wet dock and the Orwell the ground is low-lying and made, so the crane’s standing gets checked too.
Before anything is lifted
Other trades finish their part before our crew cuts anything. At a waterfront office or A14 shed, the M&E contractor kills, drains and locks each system, in writing. The refrigerant has to be recovered, and that needs an F-gas certified engineer. Any asbestos found by the survey is cleared by a licensed contractor.
Our dates follow theirs. If the new plant arrives before the old has gone, we agree with the M&E contractor where it waits and in what order the two swap.
Postcodes and areas we cover
We cover every IP postcode around the town and the districts beyond it:
- Ipswich: town centre, the waterfront, Whitehouse, Ransomes, Ravenswood and Kesgrave
- East and coast: Martlesham, Woodbridge, Felixstowe, Aldeburgh and Leiston
- North and west: Stowmarket, Needham Market, Bury St Edmunds, Diss and Sudbury
- Wider area: Colchester, Chelmsford, Norwich, Lowestoft and Great Yarmouth
We strip out plant rooms right across the UK.
Why Ipswich firms choose Synergy Lifting for plant room strip out
- Estates teams involved from the survey. On Ipswich health and school sites, hours, routes and the order in which systems swap over are agreed with the people running the building before a date is booked.
- Stops in food and grain plants. Plant rooms serving Suffolk processing sites are cleared inside the shutdown you have already planned.
- Outside and inside on the same plan. We bring the crane, the riggers and the wagons, and one lift plan covers old units out and new ones in.
- Qualified and accredited. CPCS and NPORS operators, lifts planned to BS 7121, equipment inspected under LOLER and PUWER, SSIP approved, Constructionline Gold Member, certified to ISO 9001 and ISO 14001, and members of the Construction Plant-hire Association.
More than plant room strip out
Also booked alongside Ipswich strip outs:
How a plant room strip out works
- Email us the plant list and some photos from the plant room to wherever a wagon can load.
- Our surveyor walks the route to the quay or yard, marking splits.
- A lift plan goes to you with the method statement and risk assessment, and our dates come after the systems are isolated.
- Our crew strips out the plant, moves it along protected routes and loads our wagons.
- New plant is set down, levelled and handed over for connection.
Common questions
Our plant room is in a building by the wet dock. Where does the crane go?
On a road, yard or car park beside the building, once the ground is checked. Waterfront land is low-lying and made, so outrigger loads go onto mats. If no position works, the plant is split and brought out through the building.
Can you replace the boilers in a food factory without breaking its hygiene rules?
Yes. The route is agreed with your hygiene team at survey, floors and doors along it are sheeted, and our crew follows the site’s clothing rules.
Can the building stay open while the plant comes out?
Usually, yes. Most of this work happens in buildings that keep running, so the route is protected, the hours are agreed with the building manager, and the heavy moves go at night or over a weekend where that suits everyone. On a heating or cooling system the building cannot lose, the new plant goes in and is proven before the old plant comes out.
Who isolates and drains the plant before you start?
Your M&E contractor, with the isolation, drain down and lock-off signed off in writing before we cut anything. Refrigerant recovery belongs to an F-gas certified engineer and asbestos to a licensed contractor, so we plan our dates around both. We agree at quoting stage who is covering what.
Get a quote for a plant room strip out in Ipswich
- Phone: 01473 953 152
- Email: ipswich@synergy-lifting.co.uk
To price it we need the plant list, the floor it is on, whether new units follow, and pictures from the room out to the dock road or A14 yard.
We also provide plant room strip out in Norwich, Cambridge, Dover and London. See all the plant room strip out locations.