Plant Room Strip Out Liverpool

Plant room strip out in Liverpool and across Merseyside

Liverpool hospitals, schools and colleges call us when a boiler house or chiller deck is worn out. So do office landlords in the centre and manufacturers on the estates at Speke, Garston and Kirkby whose energy centres keep production running. We break the old plant down, get it out while the building stays in use and land the replacement in its place.

Our crews work across Liverpool, Bootle, Kirkby, Huyton and the Wirral, and further afield in St Helens, Widnes, Runcorn and Ormskirk. If you send photos of where the plant sits and how it would get out, we can usually quote the same day from the desk. If the building has to stay in use, we come in during evenings, weekends or a shutdown.

What a strip out covers

It covers everything from boilers and calorifiers to switchgear, with the pipework around it. Our crew cuts each item to a size its route will pass, rigs it out and loads it away, then sets the new plant on its bases. The M&E contractor sets the programme we work to, and their engineers keep the pipework, electrical work and commissioning.

What comes out of a Liverpool plant room

Plant Where it sits How it comes out
Cast iron sectional boilers Boiler houses under older buildings Taken apart section by section and carried up the stair
Air-cooled chillers Flat roofs and podium decks Craned off in one piece, or cut into modules
Packaged air handling units Rooftops and high-level plant rooms Parted at the factory joints and wheeled out
Pumps and expansion vessels Plant room floors and risers Unbolted from the plinth and trolleyed out
Transformers, switchgear and generators Yards, generator rooms and switchrooms Jacked onto skates and winched to the crane
Old pipe runs and support frames Along walls and up the risers Cut cold into lengths and crated for the wagon

In a Liverpool plant room the piece facing the worst exit picks the method, whatever the heaviest one weighs. See the plant room strip out service page.

Contact us

Get In Touch

Please leave a few details and a member of our plant room strip out team will be in touch to discuss your requirements in more detail.

    Where we work in and around Liverpool

    Where Liverpool plant room work comes from:

    Rooftop and energy centre plant at Speke, Garston and Kirkby

    Rooftop units and boiler plant come off factories and warehouses on those estates, where a stopped energy centre halts production. Kirkby’s food producers need it finished within a brief shutdown. See our industrial and food and beverages pages.

    Lecture and laboratory buildings

    Air handling units, chillers and laboratory plant leave the city’s university buildings in the holiday shutdown, before students return. See our education page.

    Hospital plant that cannot be switched off

    Chillers and air handling units are replaced in hospital buildings that stay in use, so the new plant is proven before the old leaves, on routes and hours the hospital sets. See our healthcare and pharma page.

    Office roofs in the Commercial District and the Baltic Triangle

    Chillers and condensers come off office and mixed use roofs in the centre, lifted in the evening or on a Sunday while the floors below stay let. See our HVAC page.

    School boiler houses in the summer break

    Old boiler plant leaves school and college buildings across Liverpool, Knowsley and Sefton over the summer, and the reopening date fixes the end of the job.

    Access and planning for a Liverpool plant room strip out

    The survey works through these before we price:

    • The street and a lay-down area. Craning roof plant off a central building takes part of a street and room to stage the units. We apply to Liverpool City Council for the traffic management and road closure, or to Sefton, Knowsley or Wirral Council outside the city.
    • Who is in the building while we work. Patients, students and office tenants carry on around us, so access windows, night work, noise, lift use and protected routes are fixed with the building manager first.
    • Floors, cellars and made ground. A load on skates or jacks bears hard on a small patch of slab. Riverside ground is largely reclaimed and older central streets have cellars, so the route and the crane standing are both checked.
    • How small the pieces get. Boilers split at their sections, air handling units at their panel joints, and the heaviest piece left sets the size of crane or gantry, or whether one comes at all.
    • Crane or stairs. Lifting over the roof costs a closure and a crane for the day. Carrying plant down inside costs lift time, floor protection, more hands and extra shifts.

    Before anything is lifted

    The first cut waits on other trades. Cellar or Speke roof, each system reaches us dead and empty with the locks on, backed by your M&E contractor’s written sign-off, and an F-gas certified engineer has taken out any refrigerant. The asbestos survey, and any licensed removal it calls for, is finished before we start.

    Our dates are planned around those three, and the quote says who covers each. When one runs late, we move our start to follow it and tell the M&E contractor what that does to the set-in date for the new plant.

    Postcodes and areas we cover

    We cover every L postcode, including:

    • L1 to L8: Liverpool city centre, the Commercial District, the Baltic Triangle, Toxteth, Everton and Kirkdale
    • L9 to L14: Aintree, Walton, Fazakerley, Norris Green and Knotty Ash
    • L15 to L25: Wavertree, Allerton, Garston, Speke and Woolton
    • L26 to L40: Halewood, Huyton, Prescot, Kirkby, Maghull and Ormskirk
    • Wider area: Bootle, Birkenhead and the Wirral, Widnes, Runcorn, St Helens and Warrington

    We strip out plant rooms right across the UK.

    Why Liverpool firms choose Synergy Lifting for plant room strip out

    • Plant rooms in hospitals and campuses that stay open. We change chillers, boilers and air handling units in Liverpool buildings still in use, on hours agreed with the estates team.
    • Evening and Sunday lifts in the centre. Rooftop plant in the centre comes off when the streets are quiet.
    • The whole job sits with us. We bring the crane outside and the crew in the plant room, haul the old plant away and land the new unit on its bases.
    • Qualified and accredited. CPCS and NPORS operators, lifts planned to BS 7121, equipment inspected under LOLER and PUWER, SSIP approved, Constructionline Gold Member, certified to ISO 9001 and ISO 14001, and members of the Construction Plant-hire Association.

    How a plant room strip out works

    1. Tell us what the plant is and where it sits, and send photos of the route out.
    2. On survey we agree the exit route and how small each unit has to go.
    3. The lift plan, risk assessment and method statement are drawn up to follow the isolations.
    4. The crew strips the plant out and loads it away.
    5. The replacement goes onto its bases and is handed to the M&E contractor for connection.

    Common questions

    Can chillers come off a Baltic Triangle office roof on a Sunday?

    Yes, and plenty of central lifts go then. Once the survey shows where the crane can stand, we apply for the closure with Liverpool City Council and book both for one slot.

    What if there are cellars where the crane would stand?

    We check what is beneath first. If cellars rule out the kerb, the crane stands further back on mats, or the plant comes down inside to a loading point on firmer ground.

    Can the building stay open while the plant comes out?

    Usually, yes. Most of this work happens in buildings that keep running, so the route is protected, the hours are agreed with the building manager, and the heavy moves go at night or over a weekend where that suits everyone. On a heating or cooling system the building cannot lose, the new plant goes in and is proven before the old plant comes out.

    Who isolates and drains the plant before you start?

    Your M&E contractor, with the isolation, drain down and lock-off signed off in writing before we cut anything. Refrigerant recovery belongs to an F-gas certified engineer and asbestos to a licensed contractor, so we plan our dates around both. We agree at quoting stage who is covering what.

    Get a quote for a plant room strip out in Liverpool

    Give us the plant, where it sits and what follows it, with pictures of the stair or roof hatch and the Liverpool kerb outside.

    We also provide plant room strip out in Deeside, Warrington, Wigan and Preston. See all the plant room strip out locations.