Pick a type of lifting equipment to see the maximum interval between LOLER thorough examinations and when the next one is due.

How it works

How the checker works

The interval comes from regulation 9(3)(a) of the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER): at least every 6 months for lifting accessories and equipment for lifting people, at least every 12 months for other lifting equipment, or as an examination scheme sets. The due date is that many months on from the last thorough examination.

The intervals apply to lifting equipment exposed to conditions that could make it deteriorate and lead to danger, which is nearly all lifting equipment in use.

  • At least every 6 months: lifting accessories, such as slings, chains, shackles, eyebolts, hooks, lifting beams and spreaders, clamps and lifting magnets, and a vacuum lifter moved between cranes; and equipment for lifting people, such as MEWPs, passenger lifts and hoists, and man-riding baskets (regulation 9(3)(a)(i)).
  • At least every 12 months: other lifting equipment, such as mobile, crawler, tower and overhead cranes, lorry loaders, chain blocks and lever hoists, forklifts and telehandlers, goods lifts and tail lifts, a vacuum lifter fixed to its crane, and jacks and gantries that raise a load (regulation 9(3)(a)(ii)).
  • Also lifts people: 12-month equipment that is also used to lift people, for example a crane with a man-riding basket, is 6 months. An accessory is 6 months either way.
  • An examination scheme: a competent person can draw one up with intervals to suit how and where the equipment is used. They can be longer or shorter, and the scheme’s interval then applies (regulation 9(3)(a)(iii)).

The due date is the same date that many months after the last thorough examination. Where that date does not exist, it is the last day of the month, so 31 August plus 6 months is 28 February (29 February in a leap year). The days left are counted from today’s date in the UK, and Due soon means due within 30 days.

The competent person’s report gives the latest date for the next thorough examination (LOLER Schedule 1). If it is earlier than the date here, the report’s date applies. Damage, a long time out of use and other exceptional circumstances also call for a thorough examination (regulation 9(3)(a)(iv)).

The calendar entry repeats every interval from the due date, each with a reminder 30 days before. After each examination, check the date on the new report.

The tag is 85 × 55 mm, the size of a business card, so it fits a card holder or can be laminated and fixed to the kit. Its QR code opens the result here, worked out again on the day it is scanned.

Your register is kept in this browser only: nothing is sent to us, and it is there when you come back on the same device. Clearing your browser’s site data removes it, so download it for Excel to keep a copy.

LOLER 1998, regulation 9 and Schedule 1; HSE, Thorough examinations and inspections of lifting equipment; and HSE’s guidance L113, explained in our guide to L113. Our guide to LOLER covers the rest of the Regulations. In Northern Ireland, LOLER (Northern Ireland) 1999 sets the same intervals.

FAQs

Common questions

In Great Britain, LOLER regulation 9(3) sets the longest intervals for equipment exposed to conditions that could make it deteriorate: at least every 6 months for lifting accessories and equipment for lifting people, and at least every 12 months for other lifting equipment. An examination scheme drawn up by a competent person can set different intervals.

The competent person who carries out the thorough examination. Their report must give the latest date by which the next one must be done (LOLER Schedule 1). Where the equipment has an examination scheme, its intervals apply instead of the 6 and 12 months.

LOLER defines an accessory for lifting as work equipment for attaching loads to machinery for lifting. Slings, chains, shackles, eyebolts, hooks, lifting beams and spreaders, and clamps and lifting magnets are all accessories, so each needs a thorough examination at least every 6 months.

Yes. Regulation 9(3)(a)(i) sets at least every 6 months for lifting equipment for lifting persons. In the tool, switch on Also lifts people to see that interval. The basket itself is also 6 months.

It is the longest interval the law allows from the date you enter. The date on your last thorough examination report, an examination scheme, or an event such as damage can make it due sooner. Check the report, and ask the competent person if you are unsure.

In your browser only. We do not see or store it, and it stays on that device until you remove items or clear your browser’s site data. Download for Excel saves a copy you can keep, share or open on another computer.

Planning guidance only. This does not replace an examination scheme, the date on your last thorough examination report or a competent person’s judgement. Based on LOLER 1998 regulation 9 (Great Britain).

© Synergy Lifting Ltd. The examination interval checker and its code are our own work. You are welcome to use it to plan your examinations, but please do not copy, reproduce or reuse the tool, its code or its results without our written permission.

Get a quote

Ready for a quote?

Send us the details and we will come back with a quote, usually the same day for a desktop survey.

Get a quote

Or call 0800 008 6096

  • Amazon
  • Brotje
  • ITV Studios
  • NG Bailey
  • Northern Structures
  • Schneider Electric
  • Spaans Babcock
  • Sulzer
  • Wates