Dismantling a Redundant Batching Plant at the Port of Tyne with a 50te Crane

  • Client

    Concrete manufacturer

  • Location

    Port of Tyne

  • Project Duration

    4 weeks

  • Crane

    50te mobile crane

Scroll

01. Project

A batching plant taken down and the site left clear

We dismantled a redundant concrete batching plant and its associated structures at the Port of Tyne, and removed everything from site, leaving it clear.

We were principal contractor for the job. The plant was cut into transportable sections, some around 7.5m long, and lifted down with a 50te mobile crane. As an upper-tier waste carrier, we loaded and removed all the scrap ourselves, and its value was retained against our price.

02. Resources

Cranes, plant and team

Cranes

A 50te mobile crane lifted the cut sections down and loaded them onto transport.

Plant and Equipment

MEWPs for work at height, and burning and cutting gear to cut the structure into transportable sections.

Scrap and Waste

We loaded and removed all the scrap as an upper-tier waste carrier, with its value retained against our price.

Team

Our Appointed Person planned the lifts and prepared the method statement, risk assessment and lift plan.

03. Timeline

From cutting to a clear site

04. Outcome

What it meant for the client

The client had one principal contractor for the whole job, from the first cut to a clear site, with the scrap value offset against the cost.