Plant room strip out in Durham and across County Durham
Across County Durham most of the plant rooms we empty are at energy and grid sites and on the manufacturing estates, then hospitals, university buildings and city offices. The work covers boilers, chillers, tanks, pumps, air handling units, transformers, switchgear and standby generators. Your M&E contractor holds the programme, and our crew works to it alongside theirs.
Work runs across Durham city and Chester-le-Street, out through Consett, Stanley and Crook, and south to Spennymoor, Bishop Auckland and Barnard Castle. Our nearest depot is at Darlington, twenty miles down the A1(M). A plant schedule and photographs bring a quote back the same working day, and evening, weekend and shutdown shifts suit buildings that stay in use.
What a strip out covers
We break the plant into pieces the building will let through and rig them out to the wagons. The replacement comes in by that route and goes on its bases. Pipework, electrical work and commissioning belong to the M&E contractor.
What comes out of a Durham plant room
| Plant | Where it sits | How it comes out |
|---|---|---|
| Calorifiers and boilers | Basement boiler houses | Casing off, shell cut to the doorway opening |
| Transformers, switchgear and standby generators | Energy centres and switchrooms | Unbolted, lowered onto skates, drawn out under a gantry |
| Chillers and condensers | Roof decks and external compounds | Craned off whole, or split into modules inside |
| Air handling units | Roof decks and internal risers | Split at the section joints, coils and fans singly |
| Tanks, pressurisation sets and pumps | Tank rooms and riser cupboards | Jacked and run out on rollers |
| Redundant pipework and support steel | Overhead through the room and risers | Cold cut and carried down in bundles |
Method is set by the item with the most difficult journey out, not the heaviest. The plant room strip out service page covers the rest.
Contact us
Get In Touch
Please leave a few details and a member of our plant room strip out team will be in touch to discuss your requirements in more detail.
Where we work in and around Durham
These are the buildings we get called to across the county.
Wind, solar and energy from waste sites
Transformers, switchgear and standby sets come out of compact buildings here, and on rural ground the access track decides as much as the door. Outage dates are the operator’s. See our power and renewables page.
Estates at Newton Aycliffe, Spennymoor and Consett
Boiler houses and compressor rooms behind these units go down only when production does, so the strip out sits inside a shutdown. See our industrial sector page.
The cathedral peninsula and the city centre
Boilers and air handling plant come out of old stone buildings here, from basements and roof spaces reached by one stair and a narrow door.
University and college buildings
Boilers, calorifiers and air handling plant leave the education estate inside a holiday, against a reopening date that holds. See our education page.
Hospital estates
Heating, cooling and standby power stay up while the plant behind them is swapped, so new kit is proven before old kit comes down. See our healthcare and pharma page.
Offices and mixed use in Chester-le-Street
Roof units and basement boilers come out of let buildings where every tenant uses the same goods lift and the landlord has to agree evening work. See our HVAC page.
Access and planning for a Durham plant room strip out
What we need to settle first:
- How far each unit is broken down. Taking a large unit down to its sections lowers the heaviest piece, and that weight settles the crane question.
- Working around the occupants. We agree with the building manager when we can be noisy, which goods lift we use and how the route is protected.
- Which way it leaves the building. Craning off the roof or carrying down the stairs can come out far apart on price, and the survey tells you which is cheaper.
- Crane position and lay-down. A lift over a building costs part of a road or a car park for the day, and peninsula approaches are narrow and weight restricted. Closures are through Durham County Council, and our traffic management and road closure service handles the application.
- Ground and floors under the load. Old colliery workings and made ground lie under parts of the county, and a skate under load puts a lot of weight on a small area, so we check yard routes as well as floors.
Before anything is lifted
Other trades make the plant safe first, and our dates follow theirs. The systems are isolated, drained and locked off by your M&E contractor, who confirms it in writing ahead of any cutting. Refrigerant comes out through an F-gas certified engineer, whose certificate reaches us before we touch the system.
A refurbishment and demolition survey covers asbestos, and anything it finds is cleared by a licensed contractor. Those three dates go into the programme, and our crew arrives after them.
Postcodes and areas we cover
Every DH and DL postcode, and the edges of the counties next door:
- DH1 and DH6 to DH9: Durham city, Langley Moor, Lanchester, Stanley and Consett
- DL12 to DL17: Bishop Auckland, Spennymoor, Crook, Weardale and Barnard Castle
- DH2 to DH5: Chester-le-Street, Birtley, Hetton-le-Hole and Houghton-le-Spring
- DL1 to DL5: Darlington, Newton Aycliffe and Shildon
- DL6 to DL11: Northallerton, Richmond and Catterick in North Yorkshire
We strip out plant rooms right across the UK.
Why Durham firms choose Synergy Lifting for plant room strip out
- Scope written down before you order. The quote names our part and your M&E contractor’s, so the isolations, the refrigerant recovery and the connection work each carry a name.
- Holiday and weekend shutdowns. They hold their reopening date, and the survey tells you before you commit whether the plant and the route fit inside one.
- A single contract. Our riggers break the plant down and our wagons clear it, with the crane and the replacement on the same contract.
- Qualified and accredited. CPCS and NPORS operators, lifts planned to BS 7121, equipment inspected under LOLER and PUWER, SSIP approved, Constructionline Gold Member, certified to ISO 9001 and ISO 14001, and members of the Construction Plant-hire Association.
More than plant room strip out
Services that come into a Durham strip out:
How a plant room strip out works
- Let us know the old plant, the new plant and the floor the room is on, with photographs of the route out.
- We walk the way out, decide how far each unit is broken down and note the weight left in the biggest piece.
- Lift plan, method statement and risk assessment follow, noting any weight limit on the peninsula approaches, and our days fit round the isolation dates.
- Our crew breaks the plant down, rigs it out and loads it for removal.
- The replacement goes onto its plinth, whether in a stone basement in the city or on a Spennymoor estate floor, gets levelled, and the M&E contractor connects it.
Common questions
The plant room is under a peninsula building. How does the boiler get out?
In sections, cut to suit the stair and the door at the top, or lifted through a hatch if there is one. Weight limits and the lack of room for a wagon mean the load-out goes early or late.
Our energy centre at Newton Aycliffe carries production. When would you work?
Inside the shutdown you give us, using the nights and the weekend either side. The survey tells you how much of the plant fits before restart.
Can the building stay open while the plant comes out?
Usually, yes. Most of this work happens in buildings that keep running, so the route is protected, the hours are agreed with the building manager, and the heavy moves go at night or over a weekend where that suits everyone. On a heating or cooling system the building cannot lose, the new plant goes in and is proven before the old plant comes out.
Who isolates and drains the plant before you start?
Your M&E contractor, with the isolation, drain down and lock-off signed off in writing before we cut anything. Refrigerant recovery belongs to an F-gas certified engineer and asbestos to a licensed contractor, so we plan our dates around both. We agree at quoting stage who is covering what.
Get a quote for a plant room strip out in Durham
- Phone: 0191 313 0049
- Email: durham@synergy-lifting.co.uk
Email the plant details and the floor, and say if new plant is going back in. Pictures of the stair, the door and the approach road, which near the cathedral can be narrow, help.
We also provide plant room strip out in Sunderland, Newcastle, Hartlepool and Darlington. See all the plant room strip out locations.