Scroll to top

Plant Room Strip Out Nottingham

Plant room strip out in Nottingham and across Nottinghamshire

We strip out plant rooms in Nottingham for hospital estates, schools and colleges, city-centre offices and industrial energy centres. Out comes the mechanical and electrical plant: boilers and calorifiers, chillers, air handling units, pumps and tanks, generators, transformers and switchgear, plus redundant pipework and steelwork. The replacement goes in on its bases while the building carries on around both. We work to the M&E contractor’s programme and alongside their people.

We cover Nottingham and the Lace Market, Beeston, Colwick, Bulwell and Hucknall, out to Mansfield and Newark-on-Trent. Send photographs and a plant schedule and the quote comes back the same working day, with out-of-hours and shutdown working where the building needs it.

What a strip out covers

We take the old plant apart into pieces the building will let past, move it out along the route that exists and clear it from site. New plant comes in the same way and goes down level on its bases, ready for your M&E contractor to connect.

What comes out of a Nottingham plant room

Plant Where it sits How it comes out
Boilers and calorifiers Basement and ground floor rooms Casing off, shell split at its sections, skated out
Chillers and condensers Roof plinths, podium decks and yard compounds Craned off whole, or stripped down and brought through the building
Air handling units Rooftop decks and internal risers Panels and coils unbolted, carried out a piece at a time
Pumps, pressurisation sets and tanks Tank rooms, basements and riser cupboards Gantried off their bases and skated out
Generators, transformers and switchgear Energy centres and switchrooms Jacked off the plinth, rolled out doorway by doorway
Redundant pipework and steelwork Through the room and the risers above Cold cut into lengths that clear the corners

We price off the tightest corner on the route out, not off the heaviest item in the room. More is on our plant room strip out service page.

Contact us

Get In Touch

Please leave a few details and a member of our plant room strip out team will be in touch to discuss your requirements in more detail.

    Where we work in and around Nottingham

    Who calls us in Nottingham, and what each works around:

    Chillers and air handling plant on the medical campuses

    Chillers, air handling units and boiler plant leave the medical campuses while the wards stay open. The estates team sets the route, the booking and the hours. See our healthcare and pharma page.

    Boiler houses on the Colwick and Blenheim estates

    Boilers, calorifiers and compressors come out of the plant rooms serving units at Colwick, Blenheim and Lenton, and production stops when they stop, so the job waits for a shutdown. See our industrial sector page.

    Roof and basement plant in the Lace Market and the centre

    Rooftop chillers and basement boilers leave offices and hotels with tenants still on the floors between. The streets are narrow, so the load-out takes a quiet hour. See our HVAC page.

    Process and utility plant at Beeston

    Pumps, tanks and air handling plant feeding validated areas come out around Beeston, so the route keeps clear of clean space.

    University and college plant in the vacation

    Boilers and air handling units leave the university and college estates in the vacation, and most of the load goes down through the building. See our education page.

    Access and planning for a Nottingham plant room strip out

    Settled with the building and the M&E contractor before a strip out is priced:

    • The way out sets the price. Lifting off the roof and carrying down through the building cost very differently in crane, labour and time. In the centre the tram overhead lines set a clearance, or an isolation to arrange, before a standing position is fixed.
    • How far we break it down. The panel and flange joints govern how small we can get it, and the heaviest piece left over is what brings a crane in.
    • The building carries on around us. Access windows, noise hours, which lift we get and how the route is protected, all agreed with the building manager before we take a date.
    • Point loads on old slabs. A loaded skate puts a lot of weight through a small footprint, and much of the city centre and the Lace Market has cellars underneath, so the route is checked first.
    • Closing a road, and where the plant lands. Craning over a building takes part of a road or a car park. We arrange the traffic management and road closure with Nottingham City Council or Nottinghamshire County Council.

    Before anything is lifted

    The plant is made safe by others before we touch it. Mechanical and electrical isolation, drain down and lock-off are your M&E contractor’s work, signed off in writing before we cut anything. Refrigerant is recovered by an F-gas certified engineer, and our crew is booked in behind that.

    Where a refurbishment and demolition survey identifies asbestos, a licensed contractor clears it and issues the certificates first. Our programme is built around those three dates and they sit in the quote beside ours.

    Postcodes and areas we cover

    We cover every NG postcode and the Nottinghamshire districts around it:

    • Nottingham: city centre, the Lace Market, Sneinton, Basford, Sherwood, Bulwell, Bilborough and Lenton
    • Around the city: Arnold, Colwick, West Bridgford, Wilford, Clifton, Beeston, Hucknall and Kimberley
    • The county: Mansfield, Sutton-in-Ashfield, Eastwood, Cotgrave, Bingham, Radcliffe on Trent, Southwell and Newark-on-Trent
    • Wider area: Long Eaton, Loughborough, Grantham, Worksop and Retford

    We strip out plant rooms right across the UK.

    Why Nottingham firms choose Synergy Lifting for plant room strip out

    • We work in buildings that stay open. Hospital, campus and office estates across Nottingham keep trading while we work, and the route, the hours and the lift booking are settled with the estates team.
    • A date that cannot move is ordinary work here. The survey tells you before you commit whether the vacation or the shutdown is long enough to hold the job.
    • You deal with one contractor. The lift outside, the rigging in the plant room, the removal and the new unit set on its bases all sit on one order.
    • Qualified and accredited. CPCS and NPORS operators, lifts planned to BS 7121, equipment inspected under LOLER and PUWER, SSIP approved, Constructionline Gold Member, certified to ISO 9001 and ISO 14001, and members of the Construction Plant-hire Association.

    How a plant room strip out works

    1. Send us the plant schedule, the plant room’s position in the building, the window you have and photographs of the route out.
    2. We survey and settle the method: the way out, where each item splits, and the heaviest piece once sectioned.
    3. Method statement, risk assessment and lift plan are written, and our dates fitted to the M&E contractor’s isolations.
    4. We break the plant down, rig it along the route and load it out.
    5. The replacement is set on its bases, levelled and handed over for connection.

    Common questions

    The plant room is under a Lace Market building. Will the boiler come out whole?

    The stairs, the door at the top and any hatch over the room decide it. Send photographs of the room and the way to the street and we will say where it splits.

    The chiller is on the roof with a tram line outside. Can a crane reach it?

    Yes, with the clearance from the overhead line agreed first, or an isolation arranged through the tram operator. Both take lead time, so send the address early.

    Can the building stay open while the plant comes out?

    Usually, yes. Most of this work happens in buildings that keep running, so the route is protected, the hours are agreed with the building manager, and the heavy moves go at night or over a weekend where that suits everyone. On a heating or cooling system the building cannot lose, the new plant goes in and is proven before the old plant comes out.

    Who isolates and drains the plant before you start?

    Your M&E contractor, with the isolation, drain down and lock-off signed off in writing before we cut anything. Refrigerant recovery belongs to an F-gas certified engineer and asbestos to a licensed contractor, so we plan our dates around both. We agree at quoting stage who is covering what.

    Get a quote for a plant room strip out in Nottingham

    We need to know what the plant is, where it sits and whether replacement plant is going in, plus photographs of the plant room and the route out.

    We also provide plant room strip out in Derby, Leicester, Chesterfield and Lincoln. See all the plant room strip out locations.